单项选择题
()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.
A.Planned value B.Earned value C.Actual cost D.Cost variance
单项选择题 PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.